Largest U.S. Grid Seeks to Hold Data Center Power Auction in March

Summarized by NextFin AI
  • PJM Interconnection filed an amended plan with FERC to hold a special power auction on March 1, 2027, targeting a 6,800 MW capacity shortfall driven by data-center demand.
  • The proposal shifts cost allocation toward Large Loads, requires LSE credit/collateral, and keeps exiting entities responsible for up to 15-year backstop charges, with a willingness-to-pay cap of $555 per MW-day.
  • FERC suspended the original plan as "deeply flawed" on Sept. 29; PJM's Oct. 29 filing addresses cost allocation, credit terms, and exit responsibilities, with a decision expected within 60 days.
  • PJM-exposed IPPs fell after the suspension—Constellation Energy -9.7%, Talen Energy -8.7%, Vistra -7.4%, NRG -3.3%—as markets price regulatory certainty over power prices.

NextFin News - PJM Interconnection, the operator of the largest electricity grid in the United States, has proposed holding a special power auction on March 1, 2027, to secure new generating capacity for data centers — but only if federal regulators first approve a revised plan that shifts the cost of that capacity toward the large customers creating the demand.

The amended filing, submitted to the Federal Energy Regulatory Commission on Oct. 29, 2026, resets a one-time "reliability backstop" procurement that FERC suspended five months earlier after calling the original design "deeply flawed." The bidding window would open March 1 and close March 28, 2027, with final procurement targets and supply amounts determined April 28 and results posted May 10.

The stakes extend well beyond one grid operator's calendar. The auction is the clearest test yet of how America's power system will pay for the data-center buildout — and whether regulators will let existing households and businesses subsidize the new load, or make the hyperscale customers themselves carry the reliability bill.

The Proposal: A Reset, Not a Restart

PJM's amended Reliability Backstop Generation Procurement proposal targets the roughly 6,800 megawatts of generating-capacity shortfall identified in the 2028/2029 Base Residual Auction — a gap the grid operator says is driven by the rapid rise in electricity demand from data centers and other "Large Loads" that has outpaced additions of new power supply. That figure will be recalculated before the auction using updated load forecasts and qualifying bilateral contracts already executed between large customers and generators, so the amount actually procured could be lower than the headline shortfall.

The procurement would secure capacity for up to 15 years, with a maximum willingness to pay set at a megawatt-weighted average of $555 per megawatt-day. PJM describes the process as a backfill for the capacity auction while preserving a parallel track for private bilateral contracts between Large Loads and suppliers.

At the center of Thursday's filing are modifications to three elements of the original proposal: the method for determining cost allocation for Reliability Backstop charges, credit requirements for load-serving entities, and the responsibilities of those entities if they exit PJM's market. An LSE is a regulated entity that buys or manages electrical energy supply for end-use customers.

PJM filed an amended proposal to FERC with the goal of commencing a Reliability Backstop Procurement on March 1, 2027.

The operator also asked FERC to accept the petition within 60 days. PJM serves more than 65 million customers across 13 states and the District of Columbia, stretching from the Mid-Atlantic to the Midwest. A shortfall of 6,800 MW in that footprint is roughly equivalent to losing six to seven large nuclear units — not an ongoing outage, but a forward-looking capacity-auction measurement of the supply needed to meet reliability targets for the 2028/2029 delivery year.

Why FERC Hit the Brakes — and What Changed

The March timeline is not guaranteed. On Sept. 29, FERC largely accepted PJM's initial reliability-backstop proposal but suspended its implementation for five months to resolve unresolved issues. The commission's order described the original plan as "deeply flawed" on questions of who pays, how much collateral is required, and what happens if a load-serving entity leaves the market mid-contract.

The Oct. 29 amended filing is PJM's answer to those three objections:

  • Cost allocation. Charges would now be tied to Large Load growth between the actual summer 2026 peak demand and the forecast for the 2028/2029 delivery year. Electric distribution companies must report firm Large Load growth to PJM, and costs are assigned to each zone based on that zone's contribution to the load growth.
  • Credit and collateral. The proposal requires LSEs responsible for backstop charges to post appropriate credit, including a revised lower uniform credit rate and updated payment terms — an attempt to balance protection against default with flexibility for market participants.
  • Exit responsibilities. An LSE that leaves PJM's market would remain responsible for its assigned backstop charges for the remainder of the commitment term, which can run as long as 15 years — well beyond the life of a typical retail supply contract.

Additional updates remove a prior exemption for certain municipal utilities and electric cooperatives, require at least a five-year plan for a peak-shaving adjustment opt-out, and clarify when demand response and distributed energy resources can count as qualifying offsets rather than treating every behind-the-meter battery as automatically eligible.

The cost-allocation shift responds directly to concerns raised at the commission. In a Sept. 29 concurrence, FERC Commissioner Lindsay See emphasized that existing customers should not automatically bear costs created by new demand. PJM's growth-based formula is a concrete attempt to meet that standard — though the final allocation formula has not been approved in this filing, and the retail impact still depends on state regulators, utilities, and individual customer arrangements. PJM sets wholesale market rules; it does not set retail tariffs.

This Is Structural, Not Cyclical — and That Changes the Answer

The first question any capacity shortage invites is whether it will self-correct. Here, the answer matters because it determines whether an administered auction is a necessary bridge or an unnecessary intervention.

The PJM squeeze is structural, not cyclical. A cyclical shortage is driven by a temporary shock — a cold winter, a string of plant outages, a dry hydro year — and mean-reverts once the shock passes. The evidence for a regime shift is stronger on every dimension. Demand growth from data centers is tied to AI compute buildout and hyperscale campus expansion; once a facility is connected, its load persists for the life of the asset, not a single season. The 15-year contract terms PJM is seeking acknowledge exactly that dynamic: market participants do not sign 15-year capacity deals to cover a one-year weather problem.

Three data points support the structural read. First, data centers accounted for 40% of PJM capacity costs in the last auction, according to the market monitor — a share that reflects a step-change in the load mix, not a marginal fluctuation. Second, PJM's own planning shows the shortfall has persisted across the last two capacity auctions, driven by load growth outpacing supply additions. Third, the grid operator has built parallel structural accommodations: an Expedited Interconnection Track, approved by FERC in June 2026 and opened to applications on July 31, that can advance as many as 10 qualifying generation projects per calendar year in 2026 and 2027, each providing at least 250 MW of unforced capacity and capable of reaching commercial operation within three years.

The distinction is not academic. If the shortage were cyclical, the correct response would be a short-term reliability product or emergency procurement that unwinds as supply catches up. For a structural shift, the question is not whether new capacity gets built, but who finances it and on what terms. The backstop auction is PJM's mechanism for socializing that financing across the load base — with the amended formula attempting to concentrate it on the load that caused it.

There is also a cyclical leg layered on top: natural-gas prices, interest rates, and construction lead times all affect how quickly supply can respond. But those factors modulate the pace of adjustment; they do not reverse the direction of demand. Separating the two matters, because a policy that treats a structural load shift as a cyclical blip will under-build, and one that treats every cyclical spike as structural will over-pay.

The Second-Order Trade: IPPs Are Pricing Regulatory Certainty, Not Just Power

The market has already voted once on this story, and the signal is instructive. After FERC's Sept. 29 suspension of the original auction, shares of independent power producers with generation assets in PJM fell sharply: Constellation Energy dropped 9.7%, Talen Energy fell 8.7%, Vistra Corp. declined 7.4%, and NRG Energy dipped 3.3%. Over the past 12 months, those same names have declined sharply, according to market data compiled by financial press.

The first-order read is straightforward: a delayed auction delays capacity revenue. The second-order read is more important. These stocks are not trading only the expected clearing price of megawatt-days; they are trading the certainty of the revenue stream. Nuclear and gas-fired investment plans in PJM are underwritten on long-duration capacity payments. A procurement that clears on schedule at or near the $555/MW-day willingness-to-pay cap would validate those underwriting assumptions. A further delay, or a FERC rejection that pushes the auction deeper into 2027, keeps the discount rate on that revenue elevated and raises the cost of capital for exactly the new build the region needs.

That creates an asymmetry worth watching. If FERC approves the amended filing and the March window proceeds, the equity overhang on PJM-exposed IPPs could ease even before a single megawatt is procured — because the regulatory path, not the physical electrons, is the binding constraint. Conversely, if the commission opens a new proceeding rather than accepting the filing, the same names remain exposed regardless of the underlying fundamentals of power demand.

The Counter-Thesis: Is a Centralized Auction Even Necessary?

The strongest argument against the backstop is not that the shortage is fake, but that the cure is worse than the disease. Large customers can — and do — secure supply directly. Meta Platforms' 20-year power purchase agreement with Constellation Energy's Clinton nuclear plant in Illinois is the template: a hyperscale buyer contracting for dedicated capacity without invoking a centrally administered procurement. From that vantage point, PJM's backstop is a form of central planning that picks winners, distorts locational signals, and imposes long-duration charges on customers who had no role in the decision to build the load.

FERC's own skepticism lends weight to this view. The commission did not reject the original proposal outright; it accepted it for filing but suspended implementation as "deeply flawed" — a signal that regulators may prefer market-driven bilateral solutions over an administered backstop, or at minimum want far tighter guardrails on cost socialization.

The counter-thesis has a clean falsifying signal. PJM plans to reduce the procurement target by the number of qualifying megawatts secured through executed bilateral contracts, precisely to avoid buying the same capacity twice. Watch the April 28 announcement of the final procurement target. If bilateral contracts have subtracted enough capacity to eliminate — or nearly eliminate — the shortfall, the case for a backstop procurement collapses and the counter-thesis wins: the market solved it without central intervention. If the recalculated target remains large, the structural shortage is confirmed and the auction becomes necessary infrastructure rather than regulatory overreach.

What Comes Next: Three Time Horizons

Short term — through May 2027. The story is regulatory. FERC's decision on the amended filing determines whether the March 1 bidding window opens on schedule. PJM asked for acceptance within 60 days; any deviation from that timeline, or any order opening a new technical conference or supplemental filing, is the first thing to watch.

Medium term — the 2028/2029 delivery year. The auction's clearing price and volume will set the marginal cost of capacity in the region, with the $555/MW-day maximum willingness to pay as the reference ceiling. A cleared auction near the cap flows through to capacity charges for all PJM customers, not just Large Loads, and would mark another leg in the repricing of Eastern US power that began when PJM capacity prices hit record highs after the grid operator fell short of its reliability target in December 2025.

Long term — 2029/2030 and beyond. The backstop is a bridge to a broader regime change. PJM has proposed an Interim Resource Adequacy Service, filed Aug. 13, 2026, that would apply to new Large Loads — defined as end-use customers with cumulative peak demand of at least 50 MW at a single site — beginning June 1, 2027. Under an emergency procedure, utilities could be directed to reduce or transfer demand from new Large Load customers ahead of any action that would cut off residential consumers. And beginning with the 2029/2030 capacity auction, new Large Loads that do not bring their own supply will not be included when calculating future power needs. In plain terms: the era of data centers connecting to the grid with their reliability costs socialized across all customers is ending.

Who Benefits, Who Is Exposed

  • Beneficiaries. Nuclear and flexible gas-fired generators with sites in PJM stand to gain from long-duration capacity revenue at or near the $555/MW-day reference level. Developers of new thermal and firm clean capacity gain a clearer offtake path. The March auction, if approved, converts a regulatory question into a bankable revenue stream.
  • Exposed. Data-center developers face higher and more visible interconnection costs, with the risk that their load growth — rather than the broader customer base — foots the reliability bill. Retail customers in high-growth zones carry allocation risk under the new formula. And IPP equities remain exposed to FERC's timeline risk until the filing is accepted.

The March auction is less about finding electrons than about deciding who pays for them. PJM has drawn its map; FERC holds the pen.

Explore more exclusive insights at nextfin.ai.

Insights

How does PJM grid power data centers?

Why did FERC halt PJM auction plan?

Who pays for new data center power?

What cap sets power price per day?

How does AI drive grid demand growth?

What is Meta Constellation power deal?

Are bilateral contracts enough supply?

What changes cost allocation method?

Who bears reliability bill finally?

What new rules hit large loads?

What risks face data center builders?

How does gas price affect supply build?

When does March power auction start?

Is shortage structural or cyclical?

How long are capacity contract terms?

What defines a Large Load customer?

Can market solve shortfall alone?

What happens if FERC rejects filing?

Why is regulatory certainty so key?

Who benefits from nuclear power deals?