NextFin News - The cost of building new gas-fired power in the U.S. has climbed to a 17-year high, and Lazard says the pressure is still building. That matters because gas has long been the system’s flexible bridge fuel, but turbine shortages, higher equipment costs, and longer delivery times are making new capacity materially harder to finance and deliver just as electricity demand is climbing.
In its 2025 Levelized Cost of Energy+ report, Lazard said the cost of building a new combined-cycle gas turbine has reached a 10-year high. Lazard also said turbine shortages, rising costs, and long delivery times are expected to keep pushing gas technology LCOE higher in the near term, even as productivity gains and supply-chain normalization could offset some of the pressure later. The message is not that gas is leaving the U.S. grid; it is that new gas is becoming more expensive to add at the margin.
The timing is crucial. The Energy Information Administration said U.S. electricity consumption will rise from a record 4,195 billion kilowatt-hours in 2025 to 4,269 billion in 2026 and 4,399 billion in 2027, driven by AI-hungry data centers and electrification. The EIA expects natural gas to hold a 40% share of generation in 2026 and 2027, unchanged from 2025, while coal slips from 17% to 15% and renewables rise from about 24% in 2025 to 27% in 2027. The pressure is therefore not on gas’s place in the mix, but on the cost of adding the next gas unit.
That distinction is why the story is bigger than a single fuel. The market is not simply asking whether gas remains useful; it is asking whether gas can still be built fast enough and cheaply enough to meet load growth that is now being driven by data centers, electrification, and a tighter power market. If the answer is no, utilities and regulators will have to lean more heavily on renewables, storage, transmission, demand response, and existing gas assets rather than on new-build gas. That is a structural problem because it comes from equipment scarcity, long lead times, and a demand surge that is not likely to vanish on its own.
Why New Gas Power Is Getting More Expensive
The immediate mechanism is simple: when turbines get harder to source and take longer to deliver, the all-in cost of building a plant rises. Lazard specifically pointed to turbine shortages, rising costs, and long delivery times as the forces pushing gas LCOE higher. Those inputs matter more now because power buyers are comparing gas not only with older thermal assets, but also with utility-scale solar, wind, storage, and hybrid projects that can often be deployed faster and with less fuel-price risk.
That changes the cost debate from fuel to systems engineering. A combined-cycle plant may still benefit from relatively low gas prices, but developers must now finance more expensive equipment, carry more uncertainty about delivery timing, and risk missing the windows when a plant is most valuable. In an environment where demand is rising, delay itself becomes a cost.
The second-order effect is even more important. If new gas is more expensive, the substitute is not always another gas plant. Utilities may choose more storage, more transmission upgrades, and more flexible demand management, while commercial buyers may pair intermittent generation with batteries. That shifts capital away from one large centralized asset and toward a networked resource stack. Higher gas LCOE therefore changes grid planning, not just fuel selection.
That is why this looks structural rather than purely cyclical. Some power-cost increases are driven by commodity prices and can unwind when fuel falls. This one is driven by equipment constraints, queue congestion, and a broader demand shock. Lazard’s own wording points to near-term increases, with possible long-term relief from productivity gains and supply-chain normalization. In other words, the cycle may soften, but the starting point has moved.
Historical comparison matters here. Lazard said in 2025 that new combined-cycle gas turbine costs had reached a 10-year high. Its latest framing pushes the broader U.S. gas-power cost picture to a 17-year high. That is not the profile of a passing wobble. It is a more expensive baseline, set by a tighter manufacturing market and a more aggressive load-growth outlook.
The core takeaway is that gas is still indispensable in the U.S. power mix, but new gas is becoming a much more expensive way to add reliability.
What The Market Is Already Pricing In
The relevant question is no longer whether demand exists; the EIA has already quantified that with its 4,269 billion kilowatt-hours forecast for 2026 and 4,399 billion for 2027. The real question is which technology captures the next wave of capacity additions. Lazard’s report implies that new gas is losing some of its cost edge just as the grid needs more firm supply. That is an expectation gap: the system needs speed, but gas projects are running into slow delivery and rising capital intensity.
That gap matters because price is only one part of the equation. If turbine lead times remain long, then even better financing conditions will not restore gas’s earlier economics on their own. Cheaper money cannot fully offset expensive hardware. The project schedule itself becomes part of the cost stack, and in power markets, time is often as important as dollars.
There is also a cross-industry transmission channel. Higher gas LCOE can lift spending on transmission, storage, and grid modernization. It can also make utility capital budgets larger and slower to deploy, which favors companies that build balance-sheet-heavy infrastructure and hurts developers that depend on quick turnarounds. The headline is about gas, but the effect is spread across the buildout stack.
“The cost of building a new combined cycle gas turbine has reached a 10-year high,” Lazard said in its 2025 Levelized Cost of Energy+ report.
That sentence narrows the debate. It is not saying gas is uneconomic everywhere. It is saying the marginal new gas plant now starts from a much higher cost base than it did in earlier cycles. That distinction matters for utilities deciding whether to extend existing assets, buy batteries, or order a new plant that may take years to arrive.
The strongest counter-thesis is that this is still a cyclical bottleneck rather than a lasting regime change. Lazard itself said productivity enhancements and supply-chain normalization could offset some of the increase over the longer term. If turbine manufacturing expands and delivery times shorten, the cost curve could flatten or reverse. That argument is credible because the power industry has seen supply-chain bottlenecks unwind before.
But the falsifying signal for the structural view is clear: if lead times fall materially and Lazard’s next annual analysis shows new-build gas LCOE easing rather than rising again, the regime-change thesis weakens. Until then, the burden of proof sits with anyone arguing that gas can return quickly to its old cost profile.
For now, the better read is that gas has moved from being the default answer to being one option in a much more expensive menu. The short-term effect is higher utility capital spending and more project delay. The medium-term effect is a larger role for storage, transmission, and hybrid projects. The long-term question is whether supply chains normalize fast enough to restore the economics of new-build gas before the next wave of load growth arrives.
Who Benefits, Who Is Exposed, and What Comes Next
In the near term, higher gas power costs benefit battery storage providers, transmission contractors, grid equipment makers, and developers that can bundle renewables with storage. They also help owners of existing gas plants, because extending or repowering old assets can look cheaper than greenfield construction. The exposed group is broader: utilities with large capacity shortfalls, data-center developers seeking firm power, and states that want reliability without absorbing the full cost of new thermal builds.
The medium-term implication is more strategic. If load growth keeps rising as the EIA expects, the system may not be able to rely on one dominant technology to fill the gap. Procurement decisions will increasingly be shaped by delivery time, interconnection risk, and supply-chain reliability. New gas remains part of the mix, but it now competes against a portfolio logic rather than a single cheapest-cost test.
Long term, the open question is whether this is a one-off inflationary wave or a durable shift in how U.S. power is built. If bottlenecks ease, the cost curve can stabilize. If they do not, the expensive part of power will remain the hardware and time needed to deliver firm capacity, not fuel alone.
Base case: gas stays in the mix, but new-build economics remain pressured as demand rises and equipment remains tight. Upside case for gas builders: turbine supply normalizes, delivery times shorten, and LCOE stops rising. Downside case: demand keeps outrunning grid additions, forcing higher-cost stopgaps and further inflating the cost of firm power.
The next catalysts are the next Lazard update, the next EIA demand revisions, utility procurement decisions, and any evidence that turbine lead times or capital costs are easing. If those do not improve, the 17-year-high story is not a peak. It is the new baseline.
Gas is still a bridge fuel, but the toll is rising faster than the traffic.